MEPCO New Connection Complete Process
Obtaining a new electricity connection from the MEPCO is a straightforward process, but it requires adherence to specific procedures and documentation. In this article, we will guide you about the necessary steps, requirements, and estimated time frames for securing a new connection in 2024.

What is the Procedure for MEPCO New Connection?
MEPCO provides two ways to apply for a new connection: online and in-person at designated MEPCO offices. The online application process has been streamlined to make it more accessible for consumers.
Steps to Apply for a New Connection
- Visit the Official Website: Start by navigating to the MEPCO Electricity New Connection (ENC) System website.
- Choose Application Type: Select whether you are applying for a residential, commercial, or industrial connection.
- Fill Out the Application Form: Complete the online application form with accurate details.
- Upload Required Documents: Attach scanned copies of the necessary documents (maximum file size 300 KB). These documents typically include:
- Property Document Copy
- Attested CNIC Copy of Applicant
- Attested CNIC Copy of Witness (if applicable)
- Neighbor’s Electricity Bill Copy
- Wiring Contractor’s Test Report
- Submit Your Application: After ensuring all information is correct, submit your application.

Required Documents for MEPCO New Connection
To facilitate the application process, ensure you have the following documents ready:
- Proof of Ownership: A document that verifies your ownership of the property.
- Undertaking Statement: A declaration from you as the applicant confirming no existing connections on the premises.
- No Objection Certificate (NOC): Required if there are multiple owners or if you are a tenant.
- Attested CNIC Copies: Include attested copies of your Computerized National Identity Card (CNIC) along with those of two witnesses, if necessary.
- Wiring Contractor’s Test Report: This report verifies that the wiring meets safety standards.
Estimated Time Frame for New Connections
The time required to process a new connection varies based on the load category. MEPCO categorizes connections into three main types:
Category | Load Range | Estimated Time Frame |
---|---|---|
Category One | Up to 15 kW | Approximately 30 days |
Category Two | 16 to 70 kW | Approximately 44 days |
Category Three | 71 to 500 kW | Approximately 73 days |
Detailed Steps and Time Allocation
For each category, here’s how the time is typically allocated:
Category One (Up to 15 kW)
- Application submission and receipt issuance: 1 day
- Site visit for feasibility assessment: 3 days
- Cost estimation generation: 2 days
- Demand notice issuance: 2 days
- Payment submission verification: 3 days
- Wiring test report verification: 3 days
- Service connection order issuance: 3 days
- Equipment procurement from the store: 5 days
- Meter installation by SDO/Assistant Manager Operation: 5 days
Category Two (16 to 70 kW)
The process is similar to Category One but may take longer due to increased complexity, totaling approximately 44 days.
Category Three (71 to 500 kW)
This category involves more extensive requirements and typically takes about 73 days, with additional steps for higher-capacity installations.
FAQs for MEPCO New Connection
Applying for a new connection with MEPCO is an organized process that can be completed either online or in person. By preparing the required documentation and understanding the estimated time frames based on your connection category, you can ensure a smooth application experience. For any further queries or assistance, don’t hesitate to contact MEPCO customer service or visit their official website.